United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

SOLAR + STORAGE Β· SPP

Solar + storage project GEN-2022-169, Hyde County

Solar + storage project GEN-2022-169, Hyde County is a 220 MW solar + storage request withdrawn in the SPP interconnection queue, in Hyde County, South Dakota, connecting to BEPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-169
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
LeLand Olds-Fort Thompson 345kV line
Location
Hyde County, South Dakota
Technology
Solar: 220 MW Β· Battery
Total requested
220 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
26 February 2023
Proposed online date
November 2027
Withdrawn
November 2023

Location

Marker shows the centre of Hyde County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Hyde County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem