United States βΊ Grid βΊ Interconnection queues βΊ South Dakota
SOLAR + STORAGE Β· SPPSolar + storage project GEN-2022-169, Hyde County
Solar + storage project GEN-2022-169, Hyde County is a 220 MW solar + storage request withdrawn in the SPP interconnection queue, in Hyde County, South Dakota, connecting to BEPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2023 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-169
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- BEPC
- Connection point (POI)
- LeLand Olds-Fort Thompson 345kV line
- Location
- Hyde County, South Dakota
- Technology
- Solar: 220 MW Β· Battery
- Total requested
- 220 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 26 February 2023
- Proposed online date
- November 2027
- Withdrawn
- November 2023
Location
Marker shows the centre of Hyde County; the queue data does not give exact sites.
Power plants in South Dakota Β· Transmission lines in South Dakota
Other requests in Hyde County
- Onshore wind project GEN-2016-017, Hyde CountyOnshore wind Β· 250 MW Β· built
- Onshore wind project GEN-2016-094, Hyde CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project GEN-2023-106, Hyde CountyOnshore wind Β· 504 MW Β· withdrawn
- Onshore wind project GEN-2022-068, Hyde CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2024-202, Hyde CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2022-069, Hyde CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2022-070, Hyde CountyOnshore wind Β· 250 MW Β· withdrawn
- Onshore wind project GEN-2023-105, Hyde CountyOnshore wind Β· 249 MW Β· withdrawn
- Onshore wind project GEN-2016-103, Hyde CountyOnshore wind Β· 240 MW Β· withdrawn
- Onshore wind project GEN-2018-129, Hyde CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2016-092, Hyde CountyOnshore wind Β· 175 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem