United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· SPP

Onshore wind project GEN-2017-114, Dewey County

Onshore wind project GEN-2017-114, Dewey County is a 450 MW onshore wind request withdrawn in the SPP interconnection queue, in Dewey County, South Dakota, connecting to BEPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2017 (completed)
  2. Withdrawn / abandonedSep 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-114
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
Chappelle Creek - Leland Olds 345kV
Location
Dewey County, South Dakota
Technology
Wind: 450 MW
Total requested
450 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
23 October 2017
Proposed online date
December 2021
Withdrawn
September 2022

Location

Marker shows the centre of Dewey County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Dewey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem