Solar + storage project GEN-2023-084, Brown County

Solar + storage project GEN-2023-084, Brown County is a 100 MW solar + storage request withdrawn in the SPP interconnection queue, in Brown County, South Dakota, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandonedMar 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-084
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Groton South 115 kV Substation
Location
Brown County, South Dakota
Technology
Solar: 100 MW Β· Battery
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
2 October 2023
Proposed online date
August 2028
Withdrawn
March 2024

Location

Marker shows the centre of Brown County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Brown County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem