πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· WEST

Onshore wind project GI-1214, Brown County

Onshore wind project GI-1214, Brown County is a 99.0 MW onshore wind request withdrawn in the West interconnection queue, in Brown County, South Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2012 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-1214
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Developer
Day County Wind II
Connection point (POI)
Groton 115kV
Location
Brown County, South Dakota
Technology
Wind: 99.0 MW
Total requested
99.0 MW
Service type
Other
Study phase
IAE/IAT
Queue status
Withdrawn
Entered queue
9 October 2012
Proposed online date
December 2013

Location

Marker shows the centre of Brown County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Brown County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem