United States βΊ Grid βΊ Interconnection queues βΊ South Dakota
ONSHORE WIND Β· SPPOnshore wind project GEN-2020-019, Tripp County
Onshore wind project GEN-2020-019, Tripp County is a 108 MW onshore wind request withdrawn in the SPP interconnection queue, in Tripp County, South Dakota, connecting to WAPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2020 (completed)
- Withdrawn / abandonedNov 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2020-019
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Witten Substation -Fort Randall 115 kV
- Location
- Tripp County, South Dakota
- Technology
- Wind: 108 MW
- Total requested
- 108 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 29 April 2020
- Proposed online date
- August 2027
- Withdrawn
- November 2022
Location
Marker shows the centre of Tripp County; the queue data does not give exact sites.
Power plants in South Dakota Β· Transmission lines in South Dakota
Other requests in Tripp County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem