ONSHORE WIND Β· SPP

Onshore wind project GEN-2017-020, Perkins County

Onshore wind project GEN-2017-020, Perkins County is a 250 MW onshore wind request withdrawn in the SPP interconnection queue, in Perkins County, South Dakota, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2017 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-020
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Maurine 230 kV sub
Location
Perkins County, South Dakota
Technology
Wind: 250 MW
Total requested
250 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
31 May 2017
Proposed online date
December 2020
Withdrawn
April 2020

Location

Marker shows the centre of Perkins County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Perkins County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem