United States βΊ Grid βΊ Interconnection queues βΊ South Dakota
SOLAR Β· SPPSolar project GEN-2019-006, Spink County
Solar project GEN-2019-006, Spink County is a 100 MW solar request withdrawn in the SPP interconnection queue, in Spink County, South Dakota.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2019-006
- Grid region
- SPP (Southwest Power Pool)
- Location
- Spink County, South Dakota
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 23 April 2019
- Proposed online date
- December 2022
Location
Marker shows the centre of Spink County; the queue data does not give exact sites.
Power plants in South Dakota Β· Transmission lines in South Dakota
Other requests in Spink County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem