United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

SOLAR Β· SPP

Solar project GEN-2019-006, Spink County

Solar project GEN-2019-006, Spink County is a 100 MW solar request withdrawn in the SPP interconnection queue, in Spink County, South Dakota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2019-006
Grid region
SPP (Southwest Power Pool)
Location
Spink County, South Dakota
Technology
Solar: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
23 April 2019
Proposed online date
December 2022

Location

Marker shows the centre of Spink County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Other requests in Spink County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem