United States βΊ Grid βΊ Interconnection queues βΊ South Dakota
ONSHORE WIND Β· SPPOnshore wind project GEN-2022-034, Union County
Onshore wind project GEN-2022-034, Union County is a 300 MW onshore wind request withdrawn in the SPP interconnection queue, in Union County, South Dakota, connecting to BEPC.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2022 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2025 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-034
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- BEPC
- Connection point (POI)
- Spirit Mound Station 115 kV Substation
- Location
- Union County, South Dakota
- Technology
- Wind: 300 MW
- Total requested
- 300 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 23 June 2022
- Proposed online date
- December 2025
- Came online
- December 2025
- Withdrawn
- November 2023
Location
Marker shows the centre of Union County; the queue data does not give exact sites.
Power plants in South Dakota Β· Transmission lines in South Dakota
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem