United States β€Ί Grid β€Ί Interconnection queues β€Ί South Dakota

ONSHORE WIND Β· SPP

Onshore wind project GEN-2022-034, Union County

Onshore wind project GEN-2022-034, Union County is a 300 MW onshore wind request withdrawn in the SPP interconnection queue, in Union County, South Dakota, connecting to BEPC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2022 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2025 (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-034
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
BEPC
Connection point (POI)
Spirit Mound Station 115 kV Substation
Location
Union County, South Dakota
Technology
Wind: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
23 June 2022
Proposed online date
December 2025
Came online
December 2025
Withdrawn
November 2023

Location

Marker shows the centre of Union County; the queue data does not give exact sites.

Power plants in South Dakota Β· Transmission lines in South Dakota

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem