United States βΊ Grid βΊ Interconnection queues βΊ South Dakota
ONSHORE WIND Β· SPPOnshore wind project GEN-2024-059, Stanley County
Onshore wind project GEN-2024-059, Stanley County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Stanley County, South Dakota, connecting to WAPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2024 (completed)
- Withdrawn / abandonedJul 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2024-059
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Oahe - Philip Tap 230 kV line
- Location
- Stanley County, South Dakota
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 October 2024
- Proposed online date
- December 2028
- Withdrawn
- July 2025
Location
Marker shows the centre of Stanley County; the queue data does not give exact sites.
Power plants in South Dakota Β· Transmission lines in South Dakota
Other requests in Stanley County
- Other project GI-0214, Stanley CountyOther Β· 8.0 MW Β· built
- Coal project GI-0610, Stanley CountyCoal Β· 700 MW Β· withdrawn
- Solar + storage project GEN-2023-066, Stanley CountySolar + storage Β· 130 MW Β· withdrawn
- Onshore wind project GI-0506, Stanley CountyOnshore wind Β· 100 MW Β· withdrawn
- Onshore wind project GI-0917, Stanley CountyOnshore wind Β· 99.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem