United States βΊ Grid βΊ Interconnection queues βΊ South Dakota
SOLAR Β· SPPSolar project GEN-2017-064, Oglala Lakota County
Solar project GEN-2017-064, Oglala Lakota County is a 110 MW solar request withdrawn in the SPP interconnection queue, in Oglala Lakota County, South Dakota, connecting to WAPA.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2017 (completed)
- Withdrawn / abandonedNov 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2017-064
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Underwood - Wayside 230 kV
- Location
- Oglala Lakota County, South Dakota
- Technology
- Solar: 110 MW
- Total requested
- 110 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 8 May 2017
- Proposed online date
- December 2023
- Withdrawn
- November 2021
Location
No county location in the queue data.
Power plants in South Dakota Β· Transmission lines in South Dakota
Other requests in Oglala Lakota County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem