Withdrawn queue requests in ERCOT (Texas) (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7715.0 GW
Active in queue9,218 MW45 requests
Agreement signed6,515 MW29 requests
Withdrawn7715.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

77 requests · page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
R-Cube Wind
Onshore wind · Nextera
1,000 MWWithdrawn / abandoned Denton, TXERCOT Aug 2018target 2020
Point Mountain Solar
Solar · Hecate Energy
514 MWWithdrawn / abandoned Upton, TXERCOT Apr 2018target 2020
Juno Storage
Other · Intersect Power
495 MWWithdrawn / abandoned Borden, TXERCOT Aug 2018target 2021
Ponta Power Plant
Gas · Pro Energy Services LLC
484 MWWithdrawn / abandoned Cherokee, TXERCOT Dec 2018target 2020
Spectrum Solar
Solar · IP Spectrum, LLC
400 MWWithdrawn / abandoned Comanche, TXERCOT Nov 2018target 2023
Black Angus
Onshore wind · Apex Clean
353 MWWithdrawn / abandoned Webb, TXERCOT Mar 2018target 2020
Azure Sky Wind 1
Onshore wind · Tradewind Energy
350 MWWithdrawn / abandoned Throckmorton, TXERCOT Jun 2018target 2020
Gusty Hill Wind
Onshore wind · Gusty Hill Wind Project, LLC
350 MWWithdrawn / abandoned Culberson, TXERCOT Jun 2018target 2022
Elrond
Solar · IP Elrond, LLC
313 MWWithdrawn / abandoned Haskell, TXERCOT Sep 2018target 2021
Lumina Solar
Solar · IP Lumina, LLC
313 MWWithdrawn / abandoned Scurry, TXERCOT Sep 2018target 2022
Great Dane Wind
Onshore wind · Seventus
303 MWWithdrawn / abandoned Wharton, TXERCOT Jan 2018target 2020
Fort McKavett Wind
Onshore wind · Nextera
300 MWWithdrawn / abandoned Menard, TXERCOT Aug 2018target 2020
Tiger Wind
Onshore wind · Nextera
300 MWWithdrawn / abandoned Taylor, TXERCOT Oct 2018target 2022
Callisto
Solar · Intersect Power
300 MWWithdrawn / abandoned Borden, TXERCOT Apr 2018target 2021
Double R Solar
Solar · Double R Solar Farm
280 MWWithdrawn / abandoned Kaufman, TXERCOT Nov 2018target 2021
El Zorro Solar
Solar · Cypress Creek Renewables
253 MWWithdrawn / abandoned Webb, TXERCOT Jun 2018target 2021
Highwire Solar
Solar · Cypress Creek Renewables
249 MWWithdrawn / abandoned ERCOT Mar 2018target 2020
Loma Pinta II
Onshore wind · Enerverse
202 MWWithdrawn / abandoned La Salle, TXERCOT Feb 2018target 2021
Vaquero 2 Wind
Onshore wind · Enerverse
202 MWWithdrawn / abandoned Zapata, TXERCOT Mar 2018target 2020
Barranca Wind II
Onshore wind · Barranca Wind Energy LLC
202 MWWithdrawn / abandoned ERCOT May 2018target 2026
Barranca Wind
Onshore wind · Barranca Wind Energy LLC
202 MWWithdrawn / abandoned ERCOT May 2018target 2026
Danish Fields II Solar
Solar · Danish Fields Solar, LLC
201 MWWithdrawn / abandoned Wharton, TXERCOT May 2018target 2023
Danish Fields III Solar
Solar · Danish Fields Solar, LLC
201 MWWithdrawn / abandoned Wharton, TXERCOT May 2018target 2023
Bravepost Solar
Solar · Recurrent Energy
200 MWWithdrawn / abandoned Tom Green, TXERCOT Feb 2018target 2024
M-Bar Solar
Solar · M-Bar Solar Facility
200 MWWithdrawn / abandoned Andrews, TXERCOT Dec 2018target 2020
Cunningham Solar 2
Solar · Invenergy
200 MWWithdrawn / abandoned Lamar, TXERCOT Aug 2018target 2023
Equinox Solar 1
Solar · Invenergy Solar Project Development LLC
200 MWWithdrawn / abandoned Starr, TXERCOT Dec 2018target 2028
Alwest
Gas
200 MWWithdrawn / abandoned Anderson, TXERCOT Jul 2018
Thunder Creek
Onshore wind · Nextera
200 MWWithdrawn / abandoned Hardeman, TXERCOT Aug 2018target 2021
Walstrom
Gas · Castleman Power
200 MWWithdrawn / abandoned Austin, TXERCOT Jul 2018target 2023
Cunningham Solar 3
Solar · Invenergy
200 MWWithdrawn / abandoned Lamar, TXERCOT Aug 2018target 2023
Cunningham Solar 1
Solar · Invenergy
200 MWWithdrawn / abandoned Lamar, TXERCOT Apr 2018target 2023
Equinox Solar 2
Solar · Invenergy Solar Project Development LLC
200 MWWithdrawn / abandoned Starr, TXERCOT Dec 2018target 2026
Prairie Point Wind
Onshore wind · Nextera
200 MWWithdrawn / abandoned Grayson, TXERCOT Aug 2018target 2021
Cottonwood Bayou Solar II
Solar · Cottonwood Bayou Solar, LLC
200 MWWithdrawn / abandoned Brazoria, TXERCOT Dec 2018target 2024
Robles Solar
Solar · Cypress Creek Renewables
200 MWWithdrawn / abandoned Dimmit, TXERCOT Jul 2018target 2020
Lacy Creek Wind Phase 1
Onshore wind
200 MWWithdrawn / abandoned Glasscock, TXERCOT Aug 2018
Half Moon Solar (supsended)
Solar · Nextera
181 MWWithdrawn / abandoned Hidalgo, TXERCOT Sep 2018target 2028
Dillon Gulch Wind
Onshore wind · AES
175 MWWithdrawn / abandoned Nolan, TXERCOT Apr 2018target 2020
Dusky Solar
Solar · Cypress Creek Renewables
165 MWWithdrawn / abandoned Hill, TXERCOT Jun 2018target 2020
Cowboy Solar
Solar · AP Solar Holdings LLC
153 MWWithdrawn / abandoned Frio, TXERCOT Dec 2018target 2021
Timberwolf POI A Solar
Solar · CED Crane Solar 2, LLC
152 MWWithdrawn / abandoned Upton, TXERCOT Dec 2018target 2022
Altajac
Gas · Alta Power
150 MWWithdrawn / abandoned Cherokee, TXERCOT Jul 2018target 2021
Avocet
Gas · Alta Power Lufkin Acovet
150 MWWithdrawn / abandoned Angelina, TXERCOT Dec 2018target 2021
Osprey1
Gas · Alta Power LLC
150 MWWithdrawn / abandoned Jim Wells, TXERCOT Dec 2018target 2021
GoodAlta GT
Gas · Alta Power
150 MWWithdrawn / abandoned Navarro, TXERCOT Jul 2018target 2021
Concho Valley Solar
Solar · Merit SI
150 MWWithdrawn / abandoned Tom Green, TXERCOT Mar 2018target 2021
Thickgrass Solar
Solar · Origis Energy
149 MWWithdrawn / abandoned Matagorda, TXERCOT Jul 2018target 2021
French Goldston Solar
Solar · Belltown Power
144 MWWithdrawn / abandoned Young, TXERCOT Jan 2018target 2023
Gold Creek Solar
Solar · S Power
140 MWWithdrawn / abandoned Dawson, TXERCOT May 2018target 2021
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)