πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· ERCOT

Vaquero 2 Wind

Vaquero 2 Wind is a 202 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Zapata County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedFeb 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0055
Grid region
ERCOT (Texas)
Developer
Enerverse
Connection point (POI)
tap 345kV 8905 N Edinb - 8455 Lon Hill
Location
Zapata County, Texas
Technology
Wind: 202 MW
Total requested
202 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
14 March 2018
Proposed online date
December 2020
Withdrawn
February 2020

Location

Marker shows the centre of Zapata County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Zapata County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem