United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· ERCOTVaquero 2 Wind
Vaquero 2 Wind is a 202 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Zapata County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedFeb 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20INR0055
- Grid region
- ERCOT (Texas)
- Developer
- Enerverse
- Connection point (POI)
- tap 345kV 8905 N Edinb - 8455 Lon Hill
- Location
- Zapata County, Texas
- Technology
- Wind: 202 MW
- Total requested
- 202 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 14 March 2018
- Proposed online date
- December 2020
- Withdrawn
- February 2020
Location
Marker shows the centre of Zapata County; the queue data does not give exact sites.
Other requests in Zapata County
- Cascabel Wind 2Onshore wind Β· 198 MW Β· agreement signed
- Cascabel Wind 1Onshore wind Β· 198 MW Β· agreement signed
- Corralitos Wind 1Onshore wind Β· 196 MW Β· agreement signed
- Corralitos Wind 2Onshore wind Β· 195 MW Β· agreement signed
- Falcon BESSBattery storage Β· 517 MW Β· in study
- Freedom Falcon BESSBattery storage Β· 502 MW Β· in study
- Vaquero 1 WindOnshore wind Β· 400 MW Β· in study
- Tetris SolarSolar Β· 359 MW Β· in study
- Sierra Madre SolarSolar Β· 255 MW Β· in study
- Zelus BESSBattery storage Β· 201 MW Β· in study
- Falcon Zapata Storage 138Battery storage Β· 201 MW Β· in study
- Barrosos Creek Wind 3Onshore wind Β· 198 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem