SOLAR Β· ERCOT

M-Bar Solar

M-Bar Solar is a 200 MW solar request withdrawn in the ERCOT interconnection queue, in Andrews County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2018 (completed)
  2. Withdrawn / abandonedJun 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0201
Grid region
ERCOT (Texas)
Developer
M-Bar Solar Facility
Connection point (POI)
1141 Holt 138kV
Location
Andrews County, Texas
Technology
Solar: 200 MW
Total requested
200 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
9 December 2018
Proposed online date
July 2020
Withdrawn
June 2019

Location

Marker shows the centre of Andrews County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Andrews County