United States βΊ Grid βΊ Interconnection queues βΊ Texas
GAS Β· ERCOTGoodAlta GT
GoodAlta GT is a 150 MW gas request withdrawn in the ERCOT interconnection queue, in Navarro County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2018 (completed)
- Withdrawn / abandonedFeb 2022 (project stopped here)
- ConsentedMar 2020 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 20INR0104
- Grid region
- ERCOT (Texas)
- Developer
- Alta Power
- Connection point (POI)
- tap 138kV 3483 Goodloe - 3127 Trinidad SES
- Location
- Navarro County, Texas
- Technology
- Gas: 150 MW
- Total requested
- 150 MW
- Study phase
- IA
- Queue status
- Withdrawn
- Entered queue
- 25 July 2018
- Agreement signed
- 16 March 2020
- Proposed online date
- April 2021
- Withdrawn
- February 2022
Location
Marker shows the centre of Navarro County; the queue data does not give exact sites.
Other requests in Navarro County
- Tehuacana Creek SolarSolar + storage Β· 505 MW Β· agreement signed
- Tormes SolarSolar Β· 357 MW Β· agreement signed
- Three Canes Solar SLFSolar Β· 333 MW Β· agreement signed
- Board Creek WindOnshore wind Β· 299 MW Β· agreement signed
- Yellow Cat WindOnshore wind Β· 262 MW Β· agreement signed
- Glasgow SolarSolar + storage Β· 204 MW Β· agreement signed
- Armadillo SolarSolar Β· 200 MW Β· agreement signed
- Bluebonnet Prairie WindOnshore wind Β· 173 MW Β· agreement signed
- Cape Rich BESSBattery storage Β· 151 MW Β· agreement signed
- Gaia SolarSolar + storage Β· 144 MW Β· agreement signed
- Glasgow StorageSolar + storage Β· 101 MW Β· agreement signed
- Gaia StorageSolar + storage Β· 78.8 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem