SOLAR Β· ERCOT

French Goldston Solar

French Goldston Solar is a 144 MW solar request withdrawn in the ERCOT interconnection queue, in Young County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2018 (completed)
  2. Withdrawn / abandonedSep 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0044
Grid region
ERCOT (Texas)
Developer
Belltown Power
Connection point (POI)
tap 345kV 1430 Graham - 1445 Burwick Switch
Location
Young County, Texas
Technology
Solar: 144 MW
Total requested
144 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
2 January 2018
Proposed online date
December 2023
Withdrawn
September 2021

Location

Marker shows the centre of Young County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Young County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem