Carolina Storage Young County

Carolina Storage Young County is a 105 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Young County, Texas.

Queue statusIn planning
  1. PlanningQueued Feb 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0302
Grid region
ERCOT (Texas)
Developer
CSE Storage, LLC
Connection point (POI)
TAP 138 KV BUS AND CREAT NEW BUS BETWEEN MURRAY (792) AND GRAHAM SES (1431) COUNTY : YOUNG
Location
Young County, Texas
Technology
Battery: 105 MW
Total requested
105 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
27 February 2024
Proposed online date
August 2028

Location

Marker shows the centre of Young County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Young County