ONSHORE WIND · ERCOT

Trinity Hills Wind repower

Trinity Hills Wind repower is a -27.0 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Young County, Texas.

Queue statusConsented
  1. PlanningQueued Jul 2017 (completed)
  2. ConsentedOct 2018 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0019
Grid region
ERCOT (Texas)
Developer
Trinity Hills Wind Farm LLC
Connection point (POI)
17002 Garvey Rd 345kV
Location
Young County, Texas
Technology
Wind: -27.0 MW
Total requested
-27.0 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
20 July 2017
Agreement signed
17 October 2018
Proposed online date
April 2026

Location

Marker shows the centre of Young County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Young County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem