United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in ERCOT (Texas) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,158262.0 GW
Active in queue447.3 GW1,986 requests
Agreement signed119.3 GW578 requests
Withdrawn1,158262.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,158 requests · page 4 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Hecate McCamey B Solar
Solar · Hecate Energy
400 MWWithdrawn / abandoned ERCOT May 2015target 2016
Invenergy Los Ojuelos Wind
Onshore wind · Invenergy
400 MWWithdrawn / abandoned ERCOT Nov 2007target 2050
Palo Duro Wind
Onshore wind · Higher Power Energy, LLC
400 MWWithdrawn / abandoned ERCOT Feb 2009target 2050
Zapata II W
Onshore wind · Nextera
400 MWWithdrawn / abandoned Zapata, TXERCOT Jan 2016target 2019
Lacy Creek W
Onshore wind · Terra-Gen
400 MWWithdrawn / abandoned ERCOT Nov 2016target 2019
Santa Rita Solar
Solar · Invenergy
400 MWWithdrawn / abandoned Crockett, TXERCOT Nov 2016target 2022
Gulf Wind 2
Onshore wind · Wind Development Contract Co, LLC
400 MWWithdrawn / abandoned ERCOT Aug 2004target 2050
Fort Concho Wind Farm
Onshore wind · Horizon Wind Energy
400 MWWithdrawn / abandoned ERCOT Jun 2007target 2050
Los Vientos Phase III
Onshore wind · Duke Energy Generation Services
400 MWWithdrawn / abandoned ERCOT Oct 2011target 2050
Baker Ranch
Onshore wind · Higher Power Energy, LLC
400 MWWithdrawn / abandoned ERCOT Oct 2007target 2014
Vera Renewable Generation Center
Onshore wind · Airtricity
400 MWWithdrawn / abandoned ERCOT Jan 2006target 2050
Buzzing Bee Solar
Solar · ACE DevCo NC, LLC
400 MWWithdrawn / abandoned ERCOT target 2028
Gulf Wind 3
Onshore wind · Wind Development Contract Co, LLC
400 MWWithdrawn / abandoned ERCOT Aug 2004target 2050
Bedias Solar Park
Solar · Misae Energy III
400 MWWithdrawn / abandoned Grimes, TXERCOT Oct 2023target 2026
Spectrum Solar
Solar · IP Spectrum, LLC
400 MWWithdrawn / abandoned Comanche, TXERCOT Nov 2018target 2023
Hoover's Ridge Wind
Onshore wind · Clipper Windpower
400 MWWithdrawn / abandoned ERCOT Feb 2008
Powersite Karnes
Gas · Powersite
396 MWWithdrawn / abandoned ERCOT Jun 2015target 2018
Ion Solar
Solar · GSE Group LLC
384 MWWithdrawn / abandoned ERCOT May 2019target 2026
Buffalo Gap 4
Onshore wind · AES SeaWest
378 MWWithdrawn / abandoned ERCOT Jan 2007target 2050
Palacwnd
Onshore wind · Palacios Wind, LLC
367 MWWithdrawn / abandoned Matagorda, TXERCOT target 2023
Queue Power Plant
Gas · Pro Energy Services LLC
363 MWWithdrawn / abandoned Galveston, TXERCOT Jan 2019target 2021
Toland Power Plant
Gas · ProEnergy Services LLC
363 MWWithdrawn / abandoned San Patricio, TXERCOT Feb 2019target 2020
Guadalupe II
Gas · Calpine
362 MWWithdrawn / abandoned ERCOT Jun 2012target 2019
Normande Solar Farm
Solar · 8minutenergy
360 MWWithdrawn / abandoned Borden, TXERCOT Jan 2017target 2021
Tehuacana Creek BESS-Alt POI
Other · Tehuacana Creek Solar LLC
356 MWWithdrawn / abandoned Freestone, TXERCOT Oct 2022target 2025
Boxcar Solar
Solar · EDF Renewables Development, Inc.
356 MWWithdrawn / abandoned ERCOT Mar 2021target 2027
Juno BESS
Other · JUNO BESS
355 MWWithdrawn / abandoned Borden, TXERCOT Nov 2022target 2025
Orion Brangus Storage
Other · ORION BESS
355 MWWithdrawn / abandoned Milam, TXERCOT Nov 2022target 2024
Savanna Prairie Solar
Solar · Savanna Prairie Solar, LLC
355 MWWithdrawn / abandoned ERCOT Oct 2024target 2028
Black Angus
Onshore wind · Apex Clean
353 MWWithdrawn / abandoned Webb, TXERCOT Mar 2018target 2020
CPV Rattlesnake Den WindFarm
Onshore wind · CPV Renewable Energy LLC
350 MWWithdrawn / abandoned ERCOT Mar 2008
Chapman Ranch Wind 345
Onshore wind · Apex Wind
350 MWWithdrawn / abandoned ERCOT May 2009target 2016
Noble Red Bank Windpark
Onshore wind · Redbank, LLC
350 MWWithdrawn / abandoned ERCOT Apr 2007target 2014
Silver Canyon Wind Farm Ph3
Onshore wind · Horizon Wind Energy
350 MWWithdrawn / abandoned ERCOT Jan 2007target 2015
Azure Sky Wind 1
Onshore wind · Tradewind Energy
350 MWWithdrawn / abandoned Throckmorton, TXERCOT Jun 2018target 2020
Scurry County Wind III
Onshore wind · Invenergy
350 MWWithdrawn / abandoned ERCOT Mar 2007target 2050
Gusty Hill Wind
Onshore wind · Gusty Hill Wind Project, LLC
350 MWWithdrawn / abandoned Culberson, TXERCOT Jun 2018target 2022
Pecan Creek 2 Gas
Gas · NTE Energy
350 MWWithdrawn / abandoned ERCOT Mar 2015target 2018
Umbra Solar II
Solar · Saddle House Solar Project, LLC
345 MWWithdrawn / abandoned Franklin, TXERCOT Jun 2023target 2027
Hutt Wind
Onshore wind · Pioneer Natural Resources
336 MWWithdrawn / abandoned Midland, TXERCOT Sep 2017target 2023
King County Wind Farm
Onshore wind · King County Wind Energy, LLC
332 MWWithdrawn / abandoned ERCOT Jun 2010target 2050
Dexter Solar
Solar · 241BB 8me LLC
330 MWWithdrawn / abandoned Runnels, TXERCOT Mar 2019target 2023
Dexter Storage
Other · 241BB 8ME LLC
325 MWWithdrawn / abandoned Runnels, TXERCOT Aug 2019target 2023
Christoval Solar
Solar · Bridgelink Cave Springs LLC
324 MWWithdrawn / abandoned Tom Green, TXERCOT Feb 2021target 2024
Apex Bethel CAES
Battery storage · Apex CAES
324 MWWithdrawn / abandoned ERCOT Nov 2011target 2020
Hale 1
Onshore wind · NextEra Energy
322 MWWithdrawn / abandoned Hale, TXERCOT Apr 2019target 2020
Panhandle Wind
Onshore wind · Pattern Panhandle Wind, LLC
322 MWWithdrawn / abandoned ERCOT Jul 2012target 2015
Hale Community W 1
Onshore wind · Nextera
322 MWWithdrawn / abandoned Hale, TXERCOT Nov 2013target 2020
Adams Brook Storage
Other · Adams Creek Solar Project, LLC
314 MWWithdrawn / abandoned Wilbarger, TXERCOT Feb 2024target 2027
Elrond
Solar · IP Elrond, LLC
313 MWWithdrawn / abandoned Haskell, TXERCOT Sep 2018target 2021
Page 4 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)