Hale 1

Hale 1 is a 322 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Hale County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2019 (completed)
  2. Withdrawn / abandonedApr 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0264
Grid region
ERCOT (Texas)
Developer
NextEra Energy
Connection point (POI)
23920 Abernathy 345kV
Location
Hale County, Texas
Technology
Wind: 322 MW
Total requested
322 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
2 April 2019
Proposed online date
December 2020
Withdrawn
April 2020

Location

Marker shows the centre of Hale County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Hale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem