🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

GAS · SPP

Gas project GEN-2006-018, Hale County

Gas project GEN-2006-018, Hale County is a 168 MW gas request built and operating in the SPP interconnection queue, in Hale County, Texas, connecting to SPS.

Queue statusOperating
  1. PlanningQueued Jun 2010 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2006-018
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
TUCO 230kV
Location
Hale County, Texas
Technology
Gas: 168 MW
Total requested
168 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
1 June 2010
Proposed online date
March 2011
Came online
March 2011

Location

Marker shows the centre of Hale County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem