United States › Grid › Interconnection queues › Texas
GAS · SPPGas project GEN-2006-018, Hale County
Gas project GEN-2006-018, Hale County is a 168 MW gas request built and operating in the SPP interconnection queue, in Hale County, Texas, connecting to SPS.
Request details
- Queue ID
- GEN-2006-018
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- TUCO 230kV
- Location
- Hale County, Texas
- Technology
- Gas: 168 MW
- Total requested
- 168 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 1 June 2010
- Proposed online date
- March 2011
- Came online
- March 2011
Location
Marker shows the centre of Hale County; the queue data does not give exact sites.
Other requests in Hale County
- Black Mountain Hale GasGas · 991 MW · in study
- Old Aqueduct SolarSolar + storage · 512 MW · in study
- Onshore wind project ERAS-2025-021, Hale CountyOnshore wind · 500 MW · in study
- Old Aqueduct BattSolar + storage · 303 MW · in study
- Gas project ERAS-2025-002, Hale CountyGas · 217 MW · in study
- Elk Unit 4Gas · 210 MW · in study
- Gas project GEN-2022-147, Hale CountyGas · 203 MW · in study
- Onshore wind project GEN-2012-020, Hale CountyOnshore wind · 478 MW · built
- Gas project GEN-2012-037, Hale CountyGas · 203 MW · built
- Gas project GEN-2013-016, Hale CountyGas · 203 MW · built
- Paleo BESSOther · 201 MW · built
- Gas project GEN-2015-041, Hale CountyGas · 5.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem