GAS · ERCOT

Black Mountain Hale Gas

Black Mountain Hale Gas is a 991 MW gas request in interconnection study in the ERCOT interconnection queue, in Hale County, Texas.

Queue statusIn planning
  1. PlanningQueued Aug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
29INR0175
Grid region
ERCOT (Texas)
Developer
Fort Worth Power Core LLC
Connection point (POI)
345 kV Blackwater Draw Switch (#23920)
Location
Hale County, Texas
Technology
Gas: 991 MW
Total requested
991 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
27 August 2025
Proposed online date
September 2029

Location

Marker shows the centre of Hale County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hale County