🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

GAS · SPP

Gas project GEN-2022-147, Hale County

Gas project GEN-2022-147, Hale County is a 203 MW gas request in interconnection study in the SPP interconnection queue, in Hale County, Texas, connecting to SPS.

Queue statusIn planning
  1. PlanningQueued Feb 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingApr 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2022-147
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tuco 345kV
Location
Hale County, Texas
Technology
Gas: 203 MW
Total requested
203 MW
Service type
Energy only (ERIS)
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
21 February 2023
Proposed online date
April 2025
Came online
April 2025

Location

Marker shows the centre of Hale County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem