United States › Grid › Interconnection queues › Texas

GAS · SPP

Gas project GEN-2015-041, Hale County

Gas project GEN-2015-041, Hale County is a 5.0 MW gas request built and operating in the SPP interconnection queue, in Hale County, Texas, connecting to SPS.

Queue statusOperating
  1. PlanningQueued Sep 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2015-041
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
TUCO 345kV
Location
Hale County, Texas
Technology
Gas: 5.0 MW
Total requested
5.0 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
30 September 2015
Proposed online date
October 2019
Came online
October 2019

Location

Marker shows the centre of Hale County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem