OTHER Β· ERCOTOrion Brangus Storage
Orion Brangus Storage is a 355 MW other request withdrawn in the ERCOT interconnection queue, in Milam County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2022 (completed)
- Withdrawn / abandonedFeb 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 24INR0458
- Grid region
- ERCOT (Texas)
- Developer
- ORION BESS
- Connection point (POI)
- Tap 345kV 3687 BELL COUNTY EAST SWITCH - 39950 TNP ONE PLANT
- Location
- Milam County, Texas
- Technology
- Other: 355 MW
- Total requested
- 355 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 22 November 2022
- Proposed online date
- August 2024
- Withdrawn
- February 2024
Location
Marker shows the centre of Milam County; the queue data does not give exact sites.
Other requests in Milam County
- Sypert Branch Solar ProjectSolar Β· 261 MW Β· agreement signed
- Eastbell Milam SolarSolar Β· 245 MW Β· agreement signed
- Adelite StorageBattery storage Β· 232 MW Β· agreement signed
- Hoyte SolarSolar Β· 207 MW Β· agreement signed
- Stoneridge SolarSolar Β· 202 MW Β· agreement signed
- Yaupon Solar SLFSolar Β· 201 MW Β· agreement signed
- Camino Santiago SolarSolar Β· 196 MW Β· agreement signed
- Dos Rios Energy Storage SLFBattery storage Β· 165 MW Β· agreement signed
- Eastbell Milam Solar IISolar Β· 151 MW Β· agreement signed
- Happy Dog StorageSolar + storage Β· 105 MW Β· agreement signed
- Stoneridge BESSBattery storage Β· 102 MW Β· agreement signed
- HappyDogSolarSolar + storage Β· 85.5 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem