United States βΊ Grid βΊ Interconnection queues
BATTERY STORAGE Β· ERCOTApex Bethel CAES
Apex Bethel CAES is a 324 MW battery storage request withdrawn in the ERCOT interconnection queue.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2011 (completed)
- Withdrawn / abandonedSep 2018 (project stopped here)
- ConsentedJun 2015 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 15INR0013
- Grid region
- ERCOT (Texas)
- Developer
- Apex CAES
- Connection point (POI)
- tap 345kV 3380 Big Brown - 3133 Richland Chambers
- Technology
- Other Storage: 324 MW
- Total requested
- 324 MW
- Study phase
- IA and FIS Pending
- Queue status
- Withdrawn
- Entered queue
- 16 November 2011
- Agreement signed
- 25 June 2015
- Proposed online date
- November 2020
- Withdrawn
- September 2018
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem