Christoval Solar

Christoval Solar is a 324 MW solar request withdrawn in the ERCOT interconnection queue, in Tom Green County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandonedFeb 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0489
Grid region
ERCOT (Texas)
Developer
Bridgelink Cave Springs LLC
Connection point (POI)
76003 Big Hills 345kV
Location
Tom Green County, Texas
Technology
Solar: 324 MW
Total requested
324 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
3 February 2021
Proposed online date
June 2024
Withdrawn
February 2024

Location

Marker shows the centre of Tom Green County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas