United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTRatliff (Concho Valley) Solar
Ratliff (Concho Valley) Solar is a 160 MW solar request built and operating in the ERCOT interconnection queue, in Tom Green County, Texas.
Request details
- Queue ID
- 21INR0384
- Grid region
- ERCOT (Texas)
- Developer
- MERIT SI, LLC
- Connection point (POI)
- The crossing of SAPS to Live Oak and SAPS to Yellowjacket 138 kV lines.
- Location
- Tom Green County, Texas
- Technology
- Solar: 160 MW
- Total requested
- 160 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 7 July 2019
- Agreement signed
- 28 September 2020
- Proposed online date
- May 2023
- Came online
- May 2023
Location
Marker shows the centre of Tom Green County; the queue data does not give exact sites.
Other requests in Tom Green County
- Water Valley Wind EnergyOnshore wind · 180 MW · agreement signed
- Moon Chapel WindOnshore wind · 379 MW · in study
- Fort Concho Energy storageBattery storage · 251 MW · in study
- Hofbrau BESSBattery storage · 181 MW · in study
- Zeppelin Energy StorageBattery storage · 164 MW · in study
- Dove Creek SolarSolar + storage · 164 MW · in study
- Dove Creek StorageSolar + storage · 163 MW · in study
- Morning Glory SolarSolar · 122 MW · in study
- Knickerbocker StorageOther · 25.0 MW · suspended
- Rambler SolarSolar · 200 MW · built
- Angelo SolarSolar · 195 MW · built
- Angelo StorageOther · 103 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem