🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Water Valley Wind Energy

Water Valley Wind Energy is a 180 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Tom Green County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2019 (completed)
  2. ConsentedMar 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0247
Grid region
ERCOT (Texas)
Developer
Water Valley Wind Energy, LLC
Connection point (POI)
345 kV 76009 Twin Buttes to 76090 Divide Double Circuit
Location
Tom Green County, Texas
Technology
Wind: 180 MW
Total requested
180 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
15 January 2019
Agreement signed
17 March 2025
Proposed online date
December 2027

Location

Marker shows the centre of Tom Green County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Tom Green County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem