ONSHORE WIND Β· ERCOT

Buffalo Gap 4

Buffalo Gap 4 is a 378 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
08INR0047
Grid region
ERCOT (Texas)
Developer
AES SeaWest
Technology
Wind: 378 MW
Total requested
378 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
30 January 2007
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem