ONSHORE WIND Β· ERCOT

King County Wind Farm

King County Wind Farm is a 332 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2010 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
12INR0050
Grid region
ERCOT (Texas)
Developer
King County Wind Energy, LLC
Technology
Wind: 332 MW
Total requested
332 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
22 June 2010
Proposed online date
December 2050

Location

No county location in the queue data.