Interconnection queue in Washington — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown20758.5 GW
Active in queue58.5 GW207 requests
Agreement signed3,095 MW26 requests
Withdrawn499103.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

207 requests · page 3 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 8, Grant County
Solar
200 MWIn study Grant, WAWest Jul 2022
Onshore wind project 1 Pre Jan 2004, Kittitas County
Onshore wind
200 MWIn study Kittitas, WAWest Feb 2003target 2004
Solar + storage project 99, Franklin County
Solar + storage
200 MWIn study Franklin, WAWest Sep 2019target 2021
Onshore wind project G0819, Douglas County
Onshore wind
200 MWIn study Douglas, WAWest Nov 2022target 2027
Solar project G0645, Klickitat County
Solar
200 MWIn study Klickitat, WAWest Mar 2020target 2026
Battery storage project 103, Skagit County
Battery storage
200 MWPaused / redesign Skagit, WAWest Apr 2021target 2028
Battery storage project 60, Pierce County
Battery storage
200 MWAgreement signed Pierce, WAWest Aug 2018target 2028
Solar + storage project C1-37, Kittitas County
Solar + storage · Badger Gap PV I, LLC
199 MWPaused / redesign Kittitas, WAWest May 2021target 2024
Onshore wind project T2-027, Cowlitz County
Onshore wind
199 MWIn study Cowlitz, WAWest Sep 2025target 2027
Battery storage project CS23-12, Franklin County
Battery storage
199 MWAgreement signed Franklin, WAWest May 2023target 2029
Onshore wind project CS25-07, Whitman County
Onshore wind
199 MWIn study Whitman, WAWest Apr 2025target 2029
Gas project 54, Grays Harbor County
Gas
199 MWPaused / redesign Grays Harbor, WAWest Dec 2017target 2026
Battery storage project G0637, Klickitat County
Battery storage
190 MWIn study Klickitat, WAWest Jan 2020target 2022
Gas project 153, Skagit County
Gas
188 MWIn study Skagit, WAWest Apr 2024target 2028
Gas project 152, Whatcom County
Gas
188 MWIn study Whatcom, WAWest Apr 2024target 2028
Solar + storage project G1029, Benton County
Solar + storage
188 MWIn study Benton, WAWest Nov 2023target 2027
Solar + storage project G0843, Klickitat County
Solar + storage
180 MWIn study Klickitat, WAWest Feb 2023target 2026
Battery storage project 129, Kitsap County
Battery storage
170 MWAgreement signed Kitsap, WAWest Dec 2021target 2029
Solar project G0602, Grant County
Solar
170 MWIn study Grant, WAWest Oct 2018target 2022
Solar + storage project G0716, Benton County
Solar + storage
150 MWIn study Benton, WAWest Dec 2021target 2025
Solar project G0847, Columbia County
Solar
150 MWIn study Columbia, WAWest Feb 2023target 2024
Solar + storage project C1-40, Yakima County
Solar + storage · CG Yakima County Solar I LLC
150 MWIn study Yakima, WAWest May 2021target 2025
Solar + storage project Q60, Asotin County
Solar + storage
150 MWPaused / redesign Asotin, WAWest
Solar + storage project 60, Asotin County
Solar + storage
150 MWPaused / redesign Asotin, WAWest Jun 2018target 2025
Solar project G1001, Grant County
Solar
150 MWIn study Grant, WAWest Nov 2023target 2029
Battery storage project 102, Thurston County
Battery storage
150 MWPaused / redesign Thurston, WAWest Apr 2021target 2028
Onshore wind project G0936, Klickitat County
Onshore wind
150 MWIn study Klickitat, WAWest Sep 2023target 2025
Onshore wind project G0992, Skagit County
Onshore wind
131 MWIn study Skagit, WAWest Nov 2023target 2028
Solar + storage project G0691, Benton County
Solar + storage
130 MWIn study Benton, WAWest Sep 2021target 2023
Solar + storage project 5, Grant County
Solar + storage
130 MWAgreement signed Grant, WAWest Jul 2020
Battery storage project 139, King County
Battery storage
130 MWIn study King, WAWest Dec 2023target 2028
Battery storage project G0858, Douglas County
Battery storage
130 MWIn study Douglas, WAWest Apr 2023target 2026
Solar project G0686, Benton County
Solar
128 MWIn study Benton, WAWest Aug 2021target 2028
Battery storage project 112, Thurston County
Battery storage
127 MWAgreement signed Thurston, WAWest Jun 2021target 2029
Battery storage project 121, King County
Battery storage
125 MWPaused / redesign King, WAWest Aug 2021target 2030
Solar + storage project 1, Grant County
Solar + storage
120 MWAgreement signed Grant, WAWest Sep 2017
Onshore wind project 104, Spokane County
Onshore wind
120 MWIn study Spokane, WAWest Mar 2020target 2023
Solar + storage project G0596, Yakima County
Solar + storage
112 MWIn study Yakima, WAWest Jul 2018target 2021
Onshore wind project 13, Kittitas County
Onshore wind
104 MWAgreement signed Kittitas, WAWest Sep 2007target 2008
Solar project 55, Douglas County
Solar
101 MWPaused / redesign Douglas, WAWest Jan 2018target 2030
Solar project 56, Douglas County
Solar
101 MWPaused / redesign Douglas, WAWest Jan 2018target 2030
Battery storage project G0922, Cowlitz County
Battery storage
100 MWIn study Cowlitz, WAWest Sep 2023target 2026
Onshore wind project G0635, Benton County
Onshore wind
100 MWIn study Benton, WAWest Jan 2020target 2021
Battery storage project 145, Whatcom County
Battery storage
100 MWIn study Whatcom, WAWest Apr 2024target 2027
Battery storage project C2-204, Yakima County
Battery storage
100 MWIn study Yakima, WAWest May 2022target 2024
Battery storage project 86, Whatcom County
Battery storage
100 MWAgreement signed Whatcom, WAWest Jul 2020target 2030
Other project 6, Chelan County
Other
100 MWIn study Chelan, WAWest Oct 2023target 2027
Solar project 73, Adams County
Solar
100 MWIn study Adams, WAWest Oct 2018target 2020
Battery storage project 146, Skagit County
Battery storage
100 MWIn study Skagit, WAWest Apr 2024target 2027
Solar project G0586, Klickitat County
Solar
100 MWIn study Klickitat, WAWest Apr 2018target 2022

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20122025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)