GAS · WESTGas project 54, Grays Harbor County
Gas project 54, Grays Harbor County is a 199 MW gas request suspended in the West interconnection queue, in Grays Harbor County, Washington, connecting to Puget Sound Energy.
- PlanningQueued Dec 2017 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 54
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Puget Sound Energy
- Connection point (POI)
- Olympia 115kV Substation
- Location
- Grays Harbor County, Washington
- Technology
- Gas: 199 MW
- Total requested
- 199 MW
- Service type
- Network resource (NRIS)
- Study phase
- Suspended LGIA
- Queue status
- Suspended
- Entered queue
- 21 December 2017
- Proposed online date
- June 2026
Location
Marker shows the centre of Grays Harbor County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Grays Harbor County
- Grays Harbor 1Gas · 659 MW · built
- Grays Harbor ProjectOther · 39.0 MW · built
- Coastal Energy ProjectOnshore wind · 6.0 MW · built
- Onshore wind project G0815, Grays Harbor CountyOnshore wind · 1,000 MW · withdrawn
- Wind + storage project G0735, Grays Harbor CountyWind + storage · 1,000 MW · withdrawn
- Onshore wind project G0814, Grays Harbor CountyOnshore wind · 1,000 MW · withdrawn
- Onshore wind project G0816, Grays Harbor CountyOnshore wind · 1,000 MW · withdrawn
- Gas project G0289, Grays Harbor CountyGas · 628 MW · withdrawn
- Gas project G0321, Grays Harbor CountyGas · 290 MW · withdrawn
- Other project G0371, Grays Harbor CountyOther · 65.0 MW · withdrawn
- Gas project G0575, Grays Harbor CountyGas · 51.0 MW · withdrawn
- Onshore wind project G0360, Grays Harbor CountyOnshore wind · 6.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem