🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Washington

SOLAR + STORAGE · WEST

Solar + storage project Q60, Asotin County

Solar + storage project Q60, Asotin County is a 150 MW solar + storage request suspended in the West interconnection queue, in Asotin County, Washington, connecting to Avista Utilities.

Queue statusPaused / redesign
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q60
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Dry Creek 230kV Station
Location
Asotin County, Washington
Technology
Solar: 150 MW · Battery
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Request Status: Suspended; Facilities Study: Complete; Phase One Cluster Study: Feasibility; Phase One Re-Study: N/A; Ph
Queue status
Suspended

Location

Marker shows the centre of Asotin County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Asotin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem