United States βΊ Grid βΊ Interconnection queues βΊ Washington
SOLAR + STORAGE Β· WESTSolar + storage project C2-41, Asotin County
Solar + storage project C2-41, Asotin County is a 160 MW solar + storage request withdrawn in the West interconnection queue, in Asotin County, Washington, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2022 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- C2-41
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Talbot substation
- Location
- Asotin County, Washington
- Technology
- Solar: 160 MW Β· Battery
- Total requested
- 160 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 28 April 2022
- Proposed online date
- December 2025
Location
Marker shows the centre of Asotin County; the queue data does not give exact sites.
Power plants in Washington Β· Transmission lines in Washington
Other requests in Asotin County
- Solar + storage project Q60, Asotin CountySolar + storage Β· 150 MW Β· suspended
- Solar + storage project 60, Asotin CountySolar + storage Β· 150 MW Β· suspended
- Solar + storage project G0736, Asotin CountySolar + storage Β· 600 MW Β· withdrawn
- Horizon Wind Energy-WRidgeOnshore wind Β· 200 MW Β· withdrawn
- Solar + storage project C3-029, Asotin CountySolar + storage Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem