United States › Grid › Interconnection queues › Washington
SOLAR + STORAGE · WESTSolar + storage project 60, Asotin County
Solar + storage project 60, Asotin County is a 150 MW solar + storage request suspended in the West interconnection queue, in Asotin County, Washington, connecting to Avista Utilities.
- PlanningQueued Jun 2018 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 60
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Avista Utilities
- Connection point (POI)
- Dry Creek 230 kV station
- Location
- Asotin County, Washington
- Technology
- Solar: 150 MW · Battery
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Suspended LGIA (2/27/2023)
- Queue status
- Suspended
- Entered queue
- 4 June 2018
- Proposed online date
- September 2025
Location
Marker shows the centre of Asotin County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Asotin County
- Solar + storage project Q60, Asotin CountySolar + storage · 150 MW · suspended
- Solar + storage project G0736, Asotin CountySolar + storage · 600 MW · withdrawn
- Horizon Wind Energy-WRidgeOnshore wind · 200 MW · withdrawn
- Solar + storage project C3-029, Asotin CountySolar + storage · 200 MW · withdrawn
- Solar + storage project C2-41, Asotin CountySolar + storage · 160 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem