Onshore wind project G0635, Benton County

Onshore wind project G0635, Benton County is a 100 MW onshore wind request in interconnection study in the West interconnection queue, in Benton County, Washington.

Queue statusIn planning
  1. PlanningQueued Jan 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
G0635
Grid region
West (non-ISO utilities)
Connection point (POI)
Franklin - McNary 230 KV transmission line.
Location
Benton County, Washington
Technology
Wind: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
Facility Study
Queue status
Active
Entered queue
7 January 2020
Proposed online date
October 2021

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.