United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA (2024 requests) — page 25

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,283285.2 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,283 requests · page 25 of 26
ProjectCapacityStatusLocationRegionQueuedOnline
Zeus Rusk Solar
Solar + storage · Rusk Solar, LLC
26.8 MWIn study Rusk, TXERCOT Mar 2024target 2027
Solar project 957449, Greenwood County
Solar
26.1 MWIn study Greenwood, SCSoutheast Jun 2024
Onshore wind project PIS050, Carbon County
Onshore wind · PacifiCorp
26.0 MWIn study Carbon, WYWest Feb 2024target 2024
Solar project 957084, Darlington County
Solar
25.0 MWIn study Darlington, SCSoutheast Jun 2024
Nuclear project 627, Hamilton County
Nuclear
25.0 MWIn study Hamilton, TNSoutheast Jun 2024target 2028
Oswego Clean Energy
Solar · Oswego Clean Energy Holdings
24.9 MWIn study Oswego, NYNYISO Sep 2024target 2026
Nuclear project 637, Hamilton County
Nuclear
24.0 MWIn study Hamilton, TNSoutheast Aug 2024target 2027
Hydro project 655, Hamilton County
Hydro
24.0 MWIn study Hamilton, TNSoutheast Sep 2024target 2028
Hydro project 654, Hamilton County
Hydro
24.0 MWIn study Hamilton, TNSoutheast Sep 2024target 2028
Solar project LGE-GIS-2024-004, Mercer County
Solar
22.0 MWIn study Mercer, KYSoutheast Apr 2024target 2026
Surplus; G291
Other
21.0 MWIn study MISO Sep 2024target 2026
Battery storage project AG2-380, Queen Anne's County
Battery storage · Concho Solar I, LLC
20.0 MWIn study Queen Anne's, MDPJM Dec 2024target 2023
Geothermal project Company RA, Pershing County
Geothermal
20.0 MWIn study Pershing, NVWest Oct 2024target 2029
Solar project G1069, Harney County
Solar
20.0 MWIn study Harney, ORWest Jul 2024target 2025
Battery storage project GEN-2024-SR12, Lamoure County
Battery storage
20.0 MWIn study Lamoure, NDSPP May 2024target 2026
Geothermal project Company RB, Lander County
Geothermal
20.0 MWIn study Lander, NVWest Oct 2024target 2029
Solar + storage project PIS098, Jefferson County
Solar + storage · PacifiCorp
19.9 MWIn study Jefferson, ORWest Nov 2024target 2027
Solar + storage project PIS094, Jefferson County
Solar + storage · PacifiCorp
19.9 MWIn study Jefferson, ORWest Nov 2024target 2027
Solar project PIS099, Jefferson County
Solar · PacifiCorp
19.9 MWIn study Jefferson, ORWest Nov 2024target 2027
Solar project PIS095, Jefferson County
Solar · PacifiCorp
19.9 MWIn study Jefferson, ORWest Nov 2024target 2027
Battery Storage
Battery storage
19.3 MWIn study Windsor, VTISO-NE Feb 2024target 2029
Battery Storage
Battery storage
19.3 MWIn study Franklin, VTISO-NE Mar 2024target 2029
Shannon Wind Repower
Onshore wind · Shannon Wind, LLC
18.5 MWIn study Archer, TXERCOT Feb 2024target 2027
Gas project PIS091, Salt Lake County
Gas · PacifiCorp
17.0 MWIn study Salt Lake, UTWest Oct 2024target 2026
Gas project 957712, New Hanover County
Gas · Duke Energy Progress LLC
17.0 MWIn study New Hanover, NCSoutheast Jun 2024
Battery storage project IC-1280, Floyd County
Battery storage
15.0 MWAgreement signed Floyd, GASoutheast Apr 2024target 2027
Battery storage project G1064, Umatilla County
Battery storage
15.0 MWIn study Umatilla, ORWest Apr 2024target 2026
Other project FC100000, Pasco County
Other · Masked
13.1 MWIn study Pasco, FLSoutheast Dec 2024target 2026
Nuclear project 957251, Brunswick County
Nuclear · Duke Energy Progress LLC
13.0 MWIn study Brunswick, NCSoutheast Jun 2024
Nuclear project 957249, Brunswick County
Nuclear · Duke Energy Progress LLC
13.0 MWIn study Brunswick, NCSoutheast Jun 2024
Hydro project 458, Broadwater County
Hydro
10.4 MWIn study Broadwater, MTWest Apr 2024
Battery storage project GI-2024-08, Pueblo County
Battery storage
10.0 MWIn study Pueblo, COWest May 2024target 2026
Gas project 957699, Wayne County
Gas · Duke Energy Progress, LLC.
10.0 MWIn study Wayne, NCSoutheast Jun 2024
Empire Central BESS
Battery storage · SMT Dallas III LLC
10.0 MWAgreement signed Dallas, TXERCOT Jan 2024target 2025
Compton BESS
Battery storage · SMT Dallas VII LLC
10.0 MWIn study ERCOT Aug 2024target 2027
Atascocita BESS
Battery storage · SMT Houston XIV LLC
10.0 MWIn study ERCOT Oct 2024target 2027
Carrizo Springs BESS
Battery storage · Regis Carrizo Springs LLC
10.0 MWAgreement signed Dimmit, TXERCOT Aug 20242025
Poteet BESS
Battery storage · HEN INFRASTRUCTURE, LLC 1
10.0 MWAgreement signed Atascosa, TXERCOT Oct 2024target 2026
Lantana BESS
Battery storage · Aggreko MSR Grid PC2
10.0 MWAgreement signed Nueces, TXERCOT Apr 2024target 2026
Cuero BESS
Battery storage · CUERO BESS, LLC
10.0 MWIn study ERCOT May 2024target 2026
Solar project 24-10021, Larimer County
Solar
10.0 MWIn study Larimer, COWest Oct 2024target 2026
Gas project 957695, Wayne County
Gas · Duke Energy Progress LLC
10.0 MWIn study Wayne, NCSoutheast Jun 2024
Gas project 957694, Wayne County
Gas · Duke Energy Progress LLC
10.0 MWIn study Wayne, NCSoutheast Jun 2024
Scenic Woods BESS
Battery storage · SMT Houston V LLC
10.0 MWIn study ERCOT Oct 2024target 2027
Abilene Elmcreek BESS
Battery storage · DGSP2 LLC
9.9 MWAgreement signed Taylor, TXERCOT Sep 2024target 2026
Abilene Industrial Park BESS
Battery storage · Distributed Generation Solutions LLC
9.9 MWAgreement signed Taylor, TXERCOT Sep 2024target 2026
Hydro project 957051, Jackson County
Hydro
9.9 MWIn study Jackson, NCSoutheast Jun 2024
Cedarvale Gas
Gas · RPC Merchant LLC
9.9 MWAgreement signed Ward, TXERCOT Oct 2024target 2026
Solar project 956528, Dillon County
Solar
9.0 MWIn study Dillon, SCSoutheast Jun 2024
Gas project 957670, New Hanover County
Gas · Duke Energy Progress, LLC
8.0 MWIn study New Hanover, NCSoutheast Jun 2024
Page 25 of 26

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)