Hydro project 458, Broadwater County

Hydro project 458, Broadwater County is a 10.4 MW hydro request in interconnection study in the West interconnection queue, in Broadwater County, Montana, connecting to NorthWestern Energy.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
458
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Broadwater Substation
Location
Broadwater County, Montana
Technology
Hydro: 10.4 MW
Total requested
10.4 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
18 April 2024

Location

Marker shows the centre of Broadwater County; the queue data does not give exact sites.