Solar project 299, Broadwater County

Solar project 299, Broadwater County is a 50.0 MW solar request withdrawn in the West interconnection queue, in Broadwater County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
299
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Toston Substation
Location
Broadwater County, Montana
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study System Impact Study Facilities Study
Queue status
Withdrawn
Entered queue
11 July 2016
Proposed online date
November 2017

Location

Marker shows the centre of Broadwater County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Broadwater County