United States βΊ Grid βΊ Interconnection queues βΊ Montana
SOLAR Β· WESTSolar project 289, Broadwater County
Solar project 289, Broadwater County is a 3.0 MW solar request withdrawn in the West interconnection queue, in Broadwater County, Montana, connecting to NorthWestern Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2016 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 289
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- 12.5kV at Toston Substation
- Location
- Broadwater County, Montana
- Technology
- Solar: 3.0 MW
- Total requested
- 3.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Feasibility Study System Impact Study Facilities Study Revised Facilites Study
- Queue status
- Withdrawn
- Entered queue
- 8 June 2016
- Proposed online date
- December 2020
Location
Marker shows the centre of Broadwater County; the queue data does not give exact sites.
Other requests in Broadwater County
- Gas project 464, Broadwater CountyGas Β· 150 MW Β· in study
- Hydro project 458, Broadwater CountyHydro Β· 10.4 MW Β· in study
- Solar + storage project 416, Broadwater CountySolar + storage Β· 160 MW Β· suspended
- Battery storage project 427, Broadwater CountyBattery storage Β· 200 MW Β· withdrawn
- Solar project 299, Broadwater CountySolar Β· 50.0 MW Β· withdrawn
- Hydro project 167, Broadwater CountyHydro Β· 9.8 MW Β· withdrawn
- Solar project 200, Broadwater CountySolar Β· 3.0 MW Β· withdrawn
- Solar project 199, Broadwater CountySolar Β· 3.0 MW Β· withdrawn
- Solar project 201, Broadwater CountySolar Β· 3.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem