United States › Grid › Interconnection queues › Montana
GAS · WESTGas project 464, Broadwater County
Gas project 464, Broadwater County is a 150 MW gas request in interconnection study in the West interconnection queue, in Broadwater County, Montana, connecting to NorthWestern Energy.
Queue statusIn planning
- PlanningQueued Jun 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 464
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NorthWestern Energy
- Connection point (POI)
- Three Rivers Substation
- Location
- Broadwater County, Montana
- Technology
- Gas: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 7 June 2024
- Proposed online date
- December 2029
Location
Marker shows the centre of Broadwater County; the queue data does not give exact sites.
Other requests in Broadwater County
- Hydro project 458, Broadwater CountyHydro · 10.4 MW · in study
- Solar + storage project 416, Broadwater CountySolar + storage · 160 MW · suspended
- Battery storage project 427, Broadwater CountyBattery storage · 200 MW · withdrawn
- Solar project 299, Broadwater CountySolar · 50.0 MW · withdrawn
- Hydro project 167, Broadwater CountyHydro · 9.8 MW · withdrawn
- Solar project 200, Broadwater CountySolar · 3.0 MW · withdrawn
- Solar project 199, Broadwater CountySolar · 3.0 MW · withdrawn
- Solar project 289, Broadwater CountySolar · 3.0 MW · withdrawn
- Solar project 201, Broadwater CountySolar · 3.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem