BATTERY STORAGE · SPPBattery storage project GEN-2024-SR12, Lamoure County
Battery storage project GEN-2024-SR12, Lamoure County is a 20.0 MW battery storage request in interconnection study in the SPP interconnection queue, in Lamoure County, North Dakota, connecting to WAPA.
- PlanningQueued May 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-SR12
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Edgeley 115 kV Substation
- Location
- Lamoure County, North Dakota
- Technology
- Battery: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA PENDING
- Queue status
- Active
- Entered queue
- 21 May 2024
- Proposed online date
- October 2026
Location
Marker shows the centre of Lamoure County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Lamoure County
- Onshore wind project GI-0208, Lamoure CountyOnshore wind · 40.0 MW · built
- Onshore wind project G291, Lamoure CountyOnshore wind · 19.0 MW · built
- Onshore wind project T35, Lamoure CountyOnshore wind · 1,500 MW · withdrawn
- Onshore wind project GEN-2023-114, Lamoure CountyOnshore wind · 425 MW · withdrawn
- Onshore wind project J2327, Lamoure CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project J2367, Lamoure CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project J2368, Lamoure CountyOnshore wind · 250 MW · withdrawn
- Onshore wind project GEN-2021-024, Lamoure CountyOnshore wind · 203 MW · withdrawn
- Solar project J997, Lamoure CountySolar · 200 MW · withdrawn
- Battery storage project J2518, Lamoure CountyBattery storage · 200 MW · withdrawn
- Onshore wind project GEN-2023-192, Lamoure CountyOnshore wind · 175 MW · withdrawn