BATTERY STORAGE · SOUTHEASTBattery storage project IC-1280, Floyd County
Battery storage project IC-1280, Floyd County is a 15.0 MW battery storage request with a signed interconnection agreement in the Southeast interconnection queue, in Floyd County, Georgia, connecting to Southern Company.
Queue statusConsented
- PlanningQueued Apr 2024 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- IC-1280
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Judy Mountain - Mohawk Industries 115 kV Line
- Location
- Floyd County, Georgia
- Technology
- Battery: 15.0 MW
- Total requested
- 15.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- GIA Executed; NTP Pending
- Queue status
- Active
- Entered queue
- 15 April 2024
- Proposed online date
- October 2027
Location
Marker shows the centre of Floyd County; the queue data does not give exact sites.
Other requests in Floyd County
- Battery storage project IC-1267, Floyd CountyBattery storage · 57.5 MW · agreement signed
- Hammond SolarSolar · 225 MW · in study
- Battery storage project 25-IC-1314, Floyd CountyBattery storage · 193 MW · in study
- Gas project IC-078, Floyd CountyGas · 564 MW · withdrawn
- Gas project IC-113, Floyd CountyGas · 556 MW · withdrawn
- Gas project IC-106, Floyd CountyGas · 508 MW · withdrawn
- Gas project IC-024, Floyd CountyGas · 320 MW · withdrawn
- Solar project IC-823, Floyd CountySolar · 225 MW · withdrawn
- Solar project IC-824, Floyd CountySolar · 225 MW · withdrawn
- Battery storage project IC-1143, Floyd CountyBattery storage · 175 MW · withdrawn
- Battery storage project 25-IC-1331, Floyd CountyBattery storage · 150 MW · withdrawn
- Battery storage project 25-IC-AP, Floyd CountyBattery storage · 140 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem