πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

BATTERY STORAGE Β· ERCOT

Cuero BESS

Cuero BESS is a 10.0 MW battery storage request in interconnection study in the ERCOT interconnection queue.

Queue statusIn planning
  1. PlanningQueued May 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
25INR0675
Grid region
ERCOT (Texas)
Developer
CUERO BESS, LLC
Connection point (POI)
500 kVA, 12.47Y/7.2-0.48Y/0.277kV, 3PH, 60Hz, Z=5.75%, Liquid Filled Type, Type 3R Outdoor_x000D_ β€šΓ„Β’ Station Name: CUERO LCRA_x000D_ β€šΓ„Β’ Station Code: CUERO_x000D_ β€šΓ„Β’ BUS #: 7244_x000D_ β€šΓ„Β’ Transmis
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Study phase
No MRD
Queue status
Active
Entered queue
22 May 2024
Proposed online date
May 2026

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem