Interconnection queue in SPP (Southwest Power Pool) — page 13

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown692152.4 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

692 requests · page 13 of 14
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2019-041, Lancaster County
Solar
78.0 MWPaused / redesign Lancaster, NESPP May 2019target 2028
Battery storage project GEN-2024-310, Chaves County
Battery storage
75.0 MWIn study Chaves, NMSPP Mar 2025target 2030
Battery storage project GEN-2021-052, Muskogee County
Battery storage
75.0 MWAgreement signed Muskogee, OKSPP Apr 2021target 2031
Onshore wind project GEN-2017-105, Burt County
Onshore wind
75.0 MWAgreement signed Burt, NESPP Jul 2017target 2026
Solar project GEN-2018-004, Lea County
Solar
75.0 MWAgreement signed Lea, NMSPP Apr 2018target 2027
Solar + storage project GEN-2024-071, Cass County
Solar + storage
75.0 MWIn study Cass, TXSPP Oct 2024target 2027
Battery storage project GEN-2025-SR29, Lea County
Battery storage
75.0 MWIn study Lea, NMSPP Aug 2025target 2027
Battery storage project GEN-2024-322, Graham County
Battery storage
75.0 MWIn study Graham, KSSPP Mar 2025target 2029
Battery storage project GEN-2021-048, Lancaster County
Battery storage
75.0 MWAgreement signed Lancaster, NESPP Apr 2021target 2029
Battery storage project GEN-2023-161, Blaine County
Battery storage
74.9 MWIn study Blaine, OKSPP Oct 2023target 2027
Battery storage project GEN-2021-019, Noble County
Battery storage
74.9 MWAgreement signed Noble, OKSPP Apr 2021target 2028
Solar + storage project GEN-2020-083, Richland County
Solar + storage
74.5 MWAgreement signed Richland, MTSPP Apr 2020target 2032
Battery storage project GEN-2018-011, Kingfisher County
Battery storage
74.1 MWAgreement signed Kingfisher, OKSPP Apr 2018target 2027
Onshore wind project GEN-2018-013, Dickinson County
Onshore wind
74.1 MWAgreement signed Dickinson, KSSPP Apr 2018target 2026
Solar project GEN-2013-019, Lancaster County
Solar
73.6 MWAgreement signed Lancaster, NESPP Apr 2013target 2026
Solar project GEN-2016-167, Caddo Parish County
Solar
73.5 MWAgreement signed Caddo Parish, LASPP Nov 20162024
Solar project GEN-2017-057, Caddo Parish County
Solar
72.5 MWAgreement signed Caddo Parish, LASPP May 20172025
Solar project GEN-2017-231, Franklin County
Solar
72.5 MWAgreement signed Franklin, ARSPP Nov 2017target 2027
Battery storage project GEN-2023-SR25, Mayes County
Battery storage
72.5 MWIn study Mayes, OKSPP Jul 20232024
Battery storage project GEN-2024-SR2, Franklin County
Battery storage
72.5 MWAgreement signed Franklin, ARSPP Feb 2024target 2027
Battery storage project GEN-2024-SR3, Lincoln County
Battery storage
72.5 MWAgreement signed Lincoln, OKSPP Feb 2024target 2026
Solar project GEN-2017-230, Lincoln County
Solar
72.5 MWAgreement signed Lincoln, OKSPP Nov 2017target 2027
Solar project GEN-2017-074, Mayes County
Solar
72.5 MWAgreement signed Mayes, OKSPP May 20172025
Battery storage project GEN-2023-SR26, Mayes County
Battery storage
72.5 MWIn study Mayes, OKSPP Jul 20232024
Solar project GEN-2017-073, Mayes County
Solar
72.5 MWAgreement signed Mayes, OKSPP May 20172025
Onshore wind project GEN-2018-074, Crawford County
Onshore wind
72.0 MWAgreement signed Crawford, IASPP Oct 2018target 2028
Solar project GEN-2023-GR4, Lea County
Solar
72.0 MWAgreement signed Lea, NMSPP Jul 2023target 2026
Battery storage project GEN-2024-SR8, Greeley County
Battery storage
70.0 MWIn study Greeley, NESPP Apr 2024target 2026
Battery storage project GEN-2018-052, Lea County
Battery storage
70.0 MWAgreement signed Lea, NMSPP May 2018target 2026
Battery storage project GEN-2023-SR16, Woodward County
Battery storage
70.0 MWAgreement signed Woodward, OKSPP Apr 20232025
Onshore wind project GEN-2025-SR2, Hansford County
Onshore wind
67.2 MWIn study Hansford, TXSPP May 2025target 2028
Other project GEN-2024-231, Richardson County
Other
65.0 MWIn study Richardson, NESPP Mar 2025target 2029
Solar project GEN-2017-022, Wilson County
Solar
65.0 MWAgreement signed Wilson, KSSPP May 2017target 2027
Onshore wind project GEN-2016-071, Kay County
Onshore wind
64.6 MWAgreement signed Kay, OKSPP Mar 2016target 2028
Gas project GEN-2020-064, Jasper County
Gas
64.0 MWAgreement signed Jasper, MOSPP Apr 20202025
Gas project GEN-2024-019, Gage County
Gas
62.0 MWIn study Gage, NESPP Oct 2024target 2030
Gas project GEN-2024-017, Lancaster County
Gas
62.0 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project GEN-2020-003, Cowley County
Gas
58.0 MWAgreement signed Cowley, KSSPP Apr 2020target 2029
Solar + storage project GEN-2024-220, Caddo Parish County
Solar + storage
55.0 MWIn study Caddo Parish, LASPP Mar 2025target 2030
Onshore wind project GEN-2020-069, Cherry County
Onshore wind
52.9 MWIn study Cherry, NESPP Apr 20202025
Onshore wind project GEN-2026-PR1, Ochiltree County
Onshore wind
52.6 MWIn study Ochiltree, TXSPP Dec 2025target 2030
Solar project GEN-2017-072, Payne County
Solar
52.2 MWAgreement signed Payne, OKSPP May 20172025
Battery storage project GEN-2024-SR13, Bryan County
Battery storage
52.2 MWIn study Bryan, OKSPP May 2024target 2026
Solar project GEN-2017-232, Bryan County
Solar
52.2 MWAgreement signed Bryan, OKSPP Nov 2017target 2026
Solar project GEN-2023-135, Bowie County
Solar
52.0 MWIn study Bowie, TXSPP Oct 2023target 2026
Battery storage project GEN-2017-178, Garfield County
Battery storage
52.0 MWAgreement signed Garfield, OKSPP Nov 20172025
Solar project GEN-2013-002, Lancaster County
Solar
50.6 MWAgreement signed Lancaster, NESPP Mar 2013target 2026
Battery storage project GEN-2024-243, Crawford County
Battery storage
50.1 MWIn study Crawford, ARSPP Mar 2025target 2029
Onshore wind project GEN-2018-060, Webster County
Onshore wind
50.0 MWAgreement signed Webster, NESPP May 2018target 2026
Battery storage project GEN-2023-SR9, Crosby County
Battery storage
50.0 MWAgreement signed Crosby, TXSPP Feb 2023target 2026
Page 13 of 14

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)