United States › Grid › Interconnection queues › Kansas
GAS · SPPGas project GEN-2020-003, Cowley County
Gas project GEN-2020-003, Cowley County is a 58.0 MW gas request with a signed interconnection agreement in the SPP interconnection queue, in Cowley County, Kansas, connecting to KPP.
Queue statusConsented
- PlanningQueued Apr 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2020-003
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- KPP
- Connection point (POI)
- East Substation 69 kV
- Location
- Cowley County, Kansas
- Technology
- Gas: 58.0 MW · Diesel
- Total requested
- 58.0 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 1 April 2020
- Proposed online date
- December 2029
Location
Marker shows the centre of Cowley County; the queue data does not give exact sites.
Other requests in Cowley County
- Battery storage project GEN-2024-061, Cowley CountyBattery storage · 200 MW · in study
- Onshore wind project GEN-2011-039, Cowley CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2004-010, Cowley CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2011-002, Cowley CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2011-004, Cowley CountyOnshore wind · 150 MW · withdrawn
- Solar project GEN-2022-041, Cowley CountySolar · 100 MW · withdrawn
- Solar project GEN-2023-121, Cowley CountySolar · 50.0 MW · withdrawn
- Solar project GEN-2016-173, Cowley CountySolar · 42.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem