United States › Grid › Interconnection queues › Nebraska
OTHER · SPPOther project GEN-2024-231, Richardson County
Other project GEN-2024-231, Richardson County is a 65.0 MW other request in interconnection study in the SPP interconnection queue, in Richardson County, Nebraska, connecting to OPPD.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-231
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- S1399 5 161 kV Substation
- Location
- Richardson County, Nebraska
- Technology
- Solar: 65.0 MW · Wind
- Total requested
- 65.0 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- October 2029
Location
Marker shows the centre of Richardson County; the queue data does not give exact sites.
Other requests in Richardson County
- Onshore wind project GEN-2008-119O, Richardson CountyOnshore wind · 60.0 MW · built
- Onshore wind project GEN-2010-035, Richardson CountyOnshore wind · 160 MW · withdrawn
- Battery storage project GEN-2022-152, Richardson CountyBattery storage · 80.0 MW · withdrawn
- Onshore wind project GEN-2010-041, Richardson CountyOnshore wind · 10.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem