ONSHORE WIND Β· SPPOnshore wind project GEN-2010-035, Richardson County
Onshore wind project GEN-2010-035, Richardson County is a 160 MW onshore wind request withdrawn in the SPP interconnection queue, in Richardson County, Nebraska, connecting to OPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2010 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2010-035
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- HUMBOLT 161kV
- Location
- Richardson County, Nebraska
- Technology
- Wind: 160 MW
- Total requested
- 160 MW
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 25 June 2010
- Proposed online date
- December 2014
Location
Marker shows the centre of Richardson County; the queue data does not give exact sites.
Other requests in Richardson County
- Other project GEN-2024-231, Richardson CountyOther Β· 65.0 MW Β· in study
- Onshore wind project GEN-2008-119O, Richardson CountyOnshore wind Β· 60.0 MW Β· built
- Battery storage project GEN-2022-152, Richardson CountyBattery storage Β· 80.0 MW Β· withdrawn
- Onshore wind project GEN-2010-041, Richardson CountyOnshore wind Β· 10.3 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem