United States › Grid › Interconnection queues › Iowa

ONSHORE WIND · SPP

Onshore wind project GEN-2018-074, Crawford County

Onshore wind project GEN-2018-074, Crawford County is a 72.0 MW onshore wind request with a signed interconnection agreement in the SPP interconnection queue, in Crawford County, Iowa, connecting to WAPA.

Queue statusConsented
  1. PlanningQueued Oct 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2018-074
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Denison 230kV Substation
Location
Crawford County, Iowa
Technology
Wind: 72.0 MW
Total requested
72.0 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
31 October 2018
Proposed online date
October 2028

Location

Marker shows the centre of Crawford County; the queue data does not give exact sites.

Power plants in Iowa · Transmission lines in Iowa

Other requests in Crawford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem