Onshore wind project J896, Crawford County

Onshore wind project J896, Crawford County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Crawford County, Iowa, connecting to MIDAMERICAN ENERGY COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedJun 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J896
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY COMPANY
Connection point (POI)
Victory 161 kV Substation
Location
Crawford County, Iowa
Technology
Wind: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
October 2019
Withdrawn
June 2018

Location

Marker shows the centre of Crawford County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Crawford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem